ItEr03weeks27to40
Iteration Details >>
Iteration summary
| Story | FEA | Estimate | Spent | ToDo | Progress | Done | Overrun | Completion | Developer | Reviewer | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ItEr03S01Coordination Project coordination time | ItEr03S01Coordination | 40 | 81.5333 | 8.617 | 90% | +125% | In progress | JacoboAragunde MariaFernandezRodriguez | JacoboAragunde | |||
| ItEr03S02EnvironmentLearning Get in touch with Php and PhpReport | ItEr03S02EnvironmentLearning | 30 | 8.816 | 0 |
| 100% | -70% | Complete | MariaFernandezRodriguez | JacoboAragunde | ||
| ItEr03S03BugSolving Solve some pending bugs | ItEr03S03BugSolving | 56 | 33.8 | 0 |
| 100% | -39% | Complete | MariaFernandezRodriguez JacoboAragunde | JacoboAragunde | ||
| ItEr03S04ProjectScheduleTable Develop the projects schedulefrom table | ItEr03S04ProjectScheduleTable | 253 | 275 | 253 | 52% | +108% | In progress | MariaFernandezRodriguez | JacoboAragunde | |||
| ItEr03S05TurnoverGoals Develop the turnover goals form | ItEr03S05TurnoverGoals | 35 | 40.5 | 0.5 | 98% | +17% | In progress | JacoboAragunde | JacoboAragunde | |||
| Team totals | 414 | 439.6493 | 262.117 | 62% | +69% |
Developer velocity for iteration ItEr03weeks27to40
| Who | Assigned | Spent | Remaining | Completition | Assigned Tasks | Remaining Tasks | |
|---|---|---|---|---|---|---|---|
| MariaFernandezRodriguez | 325 | 351.8993 | 261.617 | 57% | 6 | 3 | |
| JacoboAragunde | 89 | 87.75 | 0.5 | 99% | 3 | 1 |