You are in: PhpReport > ItEr03weeks27to40 Edit - Attach

ItEr03weeks27to40

Summary Improvements in PhpReport by people in company internship during Summer'08
Team PhpReportTeam
Start 2008/07/01
End 2008/09/30


Iteration Details >>

Iteration summary

StoryFEAEstimateSpentToDoProgressDoneOverrunCompletionDeveloperReviewer
ItEr03S01Coordination
Project coordination time
ItEr03S01Coordination 4081.53338.617
  
90%+125%In progress JacoboAragunde MariaFernandezRodriguez JacoboAragunde
ItEr03S02EnvironmentLearning
Get in touch with Php and PhpReport
ItEr03S02EnvironmentLearning 308.8160
smile
100%-70%Complete MariaFernandezRodriguez JacoboAragunde
ItEr03S03BugSolving
Solve some pending bugs
ItEr03S03BugSolving 5633.80
smile
100%-39%Complete MariaFernandezRodriguez JacoboAragunde JacoboAragunde
ItEr03S04ProjectScheduleTable
Develop the projects schedulefrom table
ItEr03S04ProjectScheduleTable 253275253
  
52%+108%In progress MariaFernandezRodriguez JacoboAragunde
ItEr03S05TurnoverGoals
Develop the turnover goals form
ItEr03S05TurnoverGoals 3540.50.5
  
98%+17%In progress JacoboAragunde JacoboAragunde
Team totals 414439.6493262.117
  
62%+69%   

Developer velocity for iteration ItEr03weeks27to40

WhoAssignedSpentRemainingCompletition Assigned TasksRemaining Tasks
MariaFernandezRodriguez 325351.8993261.61757% 63
JacoboAragunde 8987.750.599% 31

div class="twikiTopicInfo twikiRevInfo twikiGrayText twikiMoved"<&/div>-->

Igalia, S.L. © A Coruña-Pontevedra (Galicia), 2001-2007 - Aviso Legal - Política de privacidad
Igalia™ is a registered trademark of Igalia, S.L. Powered by TWiki